Two methods for closed cooling tower cleaning

2021-03-11

Today we will share with you about the shutdown cleaning first.

I. Shutdown cleaning;

According to the cleaning process, sterilization and algae cleaning - cleaning with detergent - pre-film - cleaning after washing away. The total cleaning period of the program is about 8 days in the shutdown state, and the scale removal rate is more than 95%. Cleaning procedure: washing - germicidal algae cleaning - detergent scale cleaning - rinsing after cleaning - pre film.

a. Rinse with water

The purpose of water washing is to use a large flow of water to wash away the dust, sediment, algae, corrosion and other loose dirt in the system, also we can checking the leakage situation of the system at the same time. The flow rate of flushing water should be greater than 0.15 m/s, and the flushing water in the system should be drained out after flushing.

b. Sterilization, algae removal and cleaning

The purpose of sterilization and algae removal cleaning is to kill the microorganisms in the system and remove the biological mucus attached to the surface of the equipment. After the flushing water is discharged, add germicidal algicide to the system for cleaning. When the turbidity of the system tends to balance, finish the cleaning.

c. Remove scale and clean with cleaning solution

The purpose of cleaning with a cleaning solution is to dissolve scale and oxides in the system with a cleaning agent, and then dissolve them in water and wash them off. The cleaning agent will be added to the central air conditioning system, with a circulating pump circulation cleaning, and then in the highest point of the drain, in the lowest point of the drain, to avoid air resistance and guide congestion, affect the cleaning effect. When cleaning, cleaning solution concentration, metal ion (Fe2+, Fe3+, Cu2+) concentration, temperature, pH value, etc. Should be tested regularly, when the metal ion concentration tends to flat, should be completed cleaning.

d. Rinse after cleaning

The purpose of this water flushing is to flush away any residual cleaning fluid and impurities that are washed away during the washing process. Flushing is the removal of impurities and residual fluids that have been deposited in the short pipe with continuous opening of the pipe. Rinse is a continuous test of pH and turbidity and is completed when pH and turbidity level off.

e. Pre film

The purpose of the pre-film is to form a complete layer of corrosion resistant protective film on the metal surface in the activated state or the metal surface whose protective film is damaged after cleaning.